Name of Client : Kuwait Oil Company (KOC)
Estimated Budget : $480,000,000
Contract Value : $477,000,000
Facility Type : Seamless, Gas Pipeline
Sector : Gas Pipeline
Main Contractor : Joint Scientific Group Larsen & Toubro
Location : Northern Kuwait, Kuwait
Award Date : 2019-Q1
Status : Construction
Background
The Kuwait Oil Company (KOC) plans to build a gas pipeline from North Kuwait to Mina Al-Ahmadi Refinery. The pipeline is expected to have a capacity of at least 900 million cu ft per day of gas.
Project Status
As of Sep 2022, KOC has requested Central Agency for Public Tenders (CAPT) for the extension of the main contract for 242 days from April 29, 2022, to December 26, 2022.
Project Scope
The project scope includes the construction of a 48-inch seamless pipeline that will extend for 160 km and will have 30-40-inch helical welded pipes, spiral welded pipes, and the construction of a compressor station.
Project Finance
The Kuwait Oil Company is the project client.
Project Schedules
Feasibility Study: 1Q-2017
EPC ITB: 3Q-2018
EP: 1Q-2019
Construction: 4Q-2019
Commissioning: 3Q-2022
Completion: 4Q-2022