Name of Client : Abu Dhabi National Oil Company (Adnoc) LNG

Estimated Budget : $870,000,000

Facility Type : Gas Field Development

Sector : Gas

Status : Construction

Location : Das Island

PMC : Mott MacDonald

Main Contractor : Tecnicas Reunidas; Target Engineering Construction

Award Date : Q3-2018


Background

Adnoc LNG is planning to implement integrated gas development expansion E1 and E2 at Das Island. This project is part of the company's target to increase gas production to 2.4 billion standard cubic feet (SCF) per day. This project is Phase 2 of the development.


Project Status

As of March 2021, construction activities are proceeding as per schedule at the site, with completion scheduled for 2022.

Project Scope

The project scope includes new gas facilities on Das Island including the construction of a new booster compression train with a capacity of 60 million ft3/d; two feed gas compression and dehydration trains; two amine-based fuel gas treatment units with 80 million ft3/d capacity each; drying and gas treatment units; and power generation and other auxiliary services.


Project Finance

Adnoc LNG (previously known as Adgas) is the project client.


Project Schedules

Project Announced: 1Q-2012

Feasibility Study: 1Q-2012

PMC: 3Q-2015

EPC ITB: 1Q-2018

Engineering & Procurement: 3Q-2018

Construction: 2Q-2020

Completion: 1Q-2022