IRAN Projects, Budget (US$), Status, Facility Type, PMC, Main Contractor
IOOC - Kharg Gas Gathering & NGL I Plant Offshore, 1,260,000,000, Construction, NGL Plant, John Brown Engineering, Gulf Piping/PIDEC.
IPDC - National Power Plant Conversion Scheme, 750,000,000, Construction, Power, Ghods Niroo, MAPNA.
KMCC - Assaluyeh Menthol Plant, 521,000,000, Agreement Signed, Methanol, Not yet appointed, Not yet appointed.
NIGC - Bid Boland Gas Treatment Plant, 1,500,000,000, EPC Contract Negotiations, Gas Processing, Petropars Ltd., -.
NIGC - IGAT 5 Main Gas Pipeline, 650,000,000, Construction, Natural Gas Pipeline/ Network, Bonyad Mostas, Various.
NIOC - Azadegan Oilfield Development, 2,000,000,000, Pre - FEED, Production of Oil, -, Inpex/Japex/Tomen.
NIOC - Bangestan Oilfield Development, 3,000,000,000, Production Sharing Agreement , Oil Production, Not yet appointed, -.
NIOC - Iran LNG, 2,000,000,000, Project On Hold, Production of LNG, Not yet appointed, Not yet appointed.
NIOC - NIOC LNG, 2,100,000,000, PMC Bid Submission, Production of LNG, -, -.
NIOC - Pars LNG, 2,000,000,000, HOA Signed, Production of LNG, Not yet appointed, Not yet appointed.
NIOC - PEDEC - Aghajari Field Gas Injection, 450,000,000, Construction, Gas Injection, Foster Wheeler, Mehras.
NIOC - PEDEC - Aghajari Oilfield Upgrade, 800,000,000, EPC Bid Submission, Production of Oil & Gas, Not yet appointed, Not yet appointed.
NIOC - PEDEC - Darkhovin Oil Field Development, 548,000,000, Construction, Production of Oil, AGIP/NICO, KCA/NIDC/Snamprojetti/Sazeh/NPCC.
NIOC - PEDEC - Doroud Offshore Facilities Upgrade, 1,000,000,000, Construction, Offshore Oil / Gas Production, Total, -.
NIOC - PEDEC - Doroud Onshore Facilities Upgrade, 1,000,000,000, Construction, Onshore Treatment Plant, Total, Petrofac.
NIOC -PEDEC-Salman Oil & Gas Field Offshore Development, 850,000,000, Construction, Production of Oil & Gas, John Brown Hydrocarbons - Technip-Coflexip, PEDCO - Petro Iran Development Company.
NIOC - PEDEC - Salman Oil & Gas Field Onshore Facilities, 850,000,000, Construction, Gas Processing, John Brown Hydrocarbons - Technip-Coflexip, PEDCO - Petro Iran Development Company.
NIOC - Persian LNG, 4,000,000,000, HOA Signed, Production of LNG, Not yet appointed, Not yet appointed.
NIOC - Soroush Early Production Facilities, 800,000,000, Commissioning, Offshore Oil Production, Shell Exploration B.V., Shell Exploration B.V..
NIOC - Soroush Permanent Producion Facilities, 800,000,000, Oil Production, Production of Oil, Shell Exploration B.V., NPCC.
NIORDC - Abadan Refinery Upgrade, 500,000,000, EPC Tender Awaited, Oil Refinery, Foster Wheeler, -.
NIORDC - Arak Refinery Expansion, 1,500,000,000, FEED, Oil Refinery, JGC, Not yet appointed.
NIORDC - Bandar Abbas Refinery Expansion, 37,000,000,000, EPC Contract Award, Oil Refinery, NIOEC, OECC.
NIORDC - Isfahan Refinery Expansion, 1,500,000,000, Feasibility Study, Refinery, Not yet appointed, Not yet appointed.
NIORDC - Refinery Upgrade Programme Overview, 1,900,000,000, -, Refinery, Unknown, Unknown.
NPC - 4th Aromatics, 596,250,000, Construction, Aromatics, None, Toyo/LG/Sazeh.
NPC - 5th Methanol (Kharg), 3,000,000,000, Retendering, Methanol and Ammonia, Pidmco, Namvaran Consulting Engineers.
NPC - Ethane Recovery, styrene & polystyrene plants, 552,000,000, Construction, Ethane Recovery, Nagran/Linde/Sazeh/Snamprogetti/Udhe, Chegalesh/Daelim.
NPC - HD/MDPE at Olefins IX, 785,000,000, Construction, Production of MDPE, Stone & Webster, Uhde - Sazeh Consultants.
NPC - Mobin Utlilities Project, 460,000,000, Construction, Utilities, None, Technip.
NPC - Olefins IX (Ethylene & Polyethylene Plants), 935,750,000, Construction, Production of LDPE, None, Technip - Nargan Consulting.
NPC - Olefins VIII Complex, 1,300,000,000, Planning, Alpha Olefins, Not yet appointed, Not yet appointed.
NPC - Olefins X Butadiene, 795,000,000, -, Under ground Coal Gassification, Unknown, Unknown.
NPC - Olefins X HDPE Plant, 795,000,000, -, Production of HDPE, Unknown, Cementhai (CCC).
NPC - Olefins XI, 1,165,000,000, EPC Contract Award, Ethane Cracker, -, Various.
NPC - PVC Plant at Olefins VIII, 509,000,000, -, Production of PVC; E-PVC , None, Uhde - Sazeh Consultants.
NPC - Sasol GTL, 1,200,000,000, Feasibility Study, Gas to Liquids Conversion, Not yet appointed, Not yet appointed.
PETROPARS - South Pars Gas Refinery, 1,200,000,000, -, Production of Gas Condensate, None, Unknown.
PETROPARS - South Pars I Offshore Gas Development, 1,000,000,000, Construction, Gas Production, Pipeline, -, Petropars Ltd..
POGC - South Pars 11 Gas Development, 1,000,000,000, Planning, Production of Gas, Total, -.
POGC - South Pars 12 Gas Development, 3,450,000,000, Negotiations, Production of Gas, None, Petropars Ltd..
POGC - South Pars 13-14 Gas Development, 2,000,000,000, Negotiations, Production of Gas, None, Unknown.
POGC - South Pars 15-16 Onshore & Offshore Facilities, 2,000,000,000, EPC Contract Negotiations, Production of Gas, Not yet appointed, Not yet appointed.
POGC - South Pars 15-16 Onshore Facilities, 2,000,000,000, Bids Under Evaluation, Production of Gas, -, Not yet appointed.
POGC - South Pars 6-8 Offshore Gas Development, 2,500,000,000, Construction, Offshore Gas Field, Petropars Ltd, Petropars Ltd.
POGC - South Pars 6-8 Onshore Gas Development, 2500,000,000, Construction, Gas Treatment, Statoil/Petropars, Toyo/JGC/Daelim/IDRO.
POGC - South Pars 9-10 Gas Development, 1,900,000,000, Construction, Gas Processing, Kvaerner, LG/OIEC/IOEC.
POGC - South Pars Phase 17 & 18, 2,200,000,000, EPC Contract Award, Gas, Various, -.
SHELL - Gas to Liquids (GTL), 2,000,000,000, Prequalification, Gas to Liquids Conversion, MW Kellog - JGC (FEED), Not yet appointed.
TAVANIR - Zanjan IPP, 850,000,000, Retendering, Power Generation, Not yet appointed, Not yet appointed.
Trans Pakistan Pipeline, 3,500,000,000, Pre Feasibility Studies, Submarine Gas Pipeline, None, None.