Name of Client : Masdar /Dubai Electricity & Water Authority (DEWA)
Estimated Budget : $1,500,000,000
Contract Value : $1,000,000,000
Facility Type : Power Plant, Solar
Sector : Power/ Renewable
Main Contractor : Larsen and Toubro (L&T)
Location : Dubai, UAE
Award Date : 2024-Q1
BACKGROUND
Dubai Water and Electricity Authority (DEWA) has initiated a plan to develop an Independent Power Producer (IPP) project, which is Phase 6 of the Mohammed Bin Rashid Al Maktoum (MBR) solar park. DEWA has doubled the Phase 6 capacity from 900 MW to 1,800 MW. When completed, this phase will provide clean energy to approximately 540,000 residences and reduce 2.36 million tonnes of carbon emissions annually and will increase the solar park’s total production capacity to 4,660 MW.
PROJECT SCOPE
The project’s scope includes solar park and 1,800 MW capacity, and solar panels.
Scope for pipes provided by BUTTING include solar receiver pipes in material TP 321 comprises fixed lengths of 4.06 m and are produced in the dimension of 88.9 x 2.3 mm.
According to DIN EN 10217-7 / TC1 and customer specifications, the pipes are produced from cold-rolled strips. The required roughness values of Ra < 0.25 µm are achieved on two grinding machines running in parallel.
PROJECT STATUS
As of November 2025, DEWA is currently implementing the project. Construction is progressing.
PROJECT FINANCE
Masdar has signed the Power Purchase Agreement with DEWA to develop the project. DEWA will retain a 60 per cent stake in the project and be the sole off taker of the power generated from the plant.
The project financiers are Abu Dhabi Commercial Bank Commercial Bank of Dubai, First Abu Dhabi Bank HSBC, and Standard Chartered Bank Abu Dhabi Islamic Bank Warba Bank.
PROJECT SCHEDULES
Project Announced : 3Q-2021
PMC ITB : 3Q-2022
EPC ITB : 3Q-2022
PMC : 4Q-2022
EP : 1Q-2024
Construction : 3Q-2024
Commissioning : 4Q-2024
Completion : 4Q-2026