Project Name: QP - Al Shaheen Refinery
Name of Client: QP - Qatar Petroleum
Budget ($ US): 400,000,000
Main Contractor: Not yet appointed
Facility Type: Refinery
Status: EPC ITB
PMC: Technip
Location: Mesaieed
Project Status
Qatar Petroleum (QP) is planning to build a new refinery in Messaied.
As of July 2007, Technip has won the combined FEED and PMC package on the refinery project. The FEED is expected to take 12 months and construction a further three years. The contract is estimated to be valued at $60 million.
Project Scope
The scope of work consists of the construction of a new refinery with a capacity of 200,000 bpd.
Project Structure
The project client is Qatar Petroleum (QP).
Schedules for this Project
Early 2005 Initial inquiry for PMC & FEED contract
Late August 2005 Pre-FEED tender
23 October 2005 New pre-FEED con tract bids submission
23 October 2005 Bids submitted for pre- FEED contract
Late August 2006 Pre-FEED contract awarded
Mid December 2006 Tender for FEED and PMC contract issued
May 2007 Award of FEED and PMC contract
Second quarter 2008 FEED expected to be completed
Late 2008 EPC tender expected to be issued
Early 2009 Award of EPC con tract expected
Early 2012 Expected project com pletion