Name of Client : Saudi Arabian Oil Company (Aramco)
Estimated Budget : $500,000,000
Revised Budget : $1,700,000,000
Contract Value : $1,700,000,000
Facility Type : Offsites/ Utilities
Sector : Gas/ Industrial
Main Contractor : Hyundai Engineering/ Hyundai Engineering & Construction
Location : Al Jafurah, Saudi Arabia
Award Date : 2021-Q4
Background
The utilities and interconnecting facilities package are part of the Jafurah gas field development that will process up to 1.1 billion cubic feet per day (Bcfd) of unconventional (shale) raw gas from nearby areas, producing sales gas, ethane, natural gas liquids and condensate. The Jafurah gas plant is expected to be a key element of Aramco's long-term strategy to boost its unconventional gas production to 3 Bcfd during the next decade.
Project Status
As of April 2024, the construction of the project is proceeding smoothly. Additionally, on January 2024 Hyundai Engineering & Construction's construction work is progressing accordingly. Al Jaber Heavy Lift and Transport (AJHL) is contracted for installation work of the project's heavy mechanical equipment.
Project Scope
The scope of the utility package involves inlet and export facilities, interconnecting pipe racks, Sulphur recovery units, flare systems, pipeline installation, and several other related infrastructures.
Project Finance
Saudi Aramco is the project client. The consortium of Hyundai Engineering Company and Hyundai Engineering and Construction Company has secured the $1.7 billion EPC contact. Hyundai Engineering holds a 55 per cent stake in the project, with Hyundai E&C taking the remaining 45 per cent.
Project Schedules
Project Announced: 1Q-2019
EPC ITB: 1Q-2020
On Hold: 4Q-2020
EPC ITB: 3Q-2021
EP: 4Q-2021
Construction: 4Q-2022
Completion: 1Q-2025