Name of Client : ADNOC Offshore
Budget : $825,000,000
Contract Value : $825,000,000
Facility Types : Development Drilling and Production
Field Type : Brownfield
Sectors : Exploration and Upstream Production, Offshore
Main Contractor : Wood
Location : Upper Zakum, Offshore Abu Dhabi, UAE
EPC Award : Q2 – 2024
PROJECT BACKGROUND
ADNOC plans to expand the Upper Zakum offshore oilfield, located 84 kilometres off Abu Dhabi, to increase production capacity to 1.2 million barrels per day under the first phase of the UZ1000 project. The expansion forms a key component of ADNOC Group’s P5 Production Increase Plan.
PROJECT SCOPE
The Upper Zakum offshore oil field development project involves expanding and upgrading facilities across four artificial islands: Al-Ghallan, Umm Al-Anbar, Ettouk and Asseifiya.
The engineering, procurement and construction (EPC) scope includes production facilities, gas-compression systems, water-injection plants, produced-water treatment and disposal systems, pumps, pipelines and electrical substations. The project will also debottleneck water-injection facilities at the Zakum Central Complex.
Additional works include installing power cables and pipelines between Umm Al-Anbar and Zirku Island, alongside associated infrastructure.
The wider development aims to modernise Upper Zakum’s operations through artificial intelligence-enabled remote operations and electricity supplied by the UAE’s clean energy grid to reduce emissions. The use of artificial islands for drilling is also intended to enhance environmental protection.
The upgrades are designed to strengthen production infrastructure, improve operational efficiency and support more sustainable offshore oilfield operations.
PROJECT STATUS
As of September 2026, construction on the $825 million project is ongoing. Construction and modular fabrication are actively progressing. Commissioning and completion are scheduled for 2027.
PROJECT FINANCE
Abu Dhabi National Oil Company (ADNOC) Offshore is the client and operator of the project. The Upper Zakum oil field is jointly owned by three stakeholders, with ADNOC holding a 60 per cent stake, ExxonMobil owning 28 per cent, and Japan Oil Development Company (JODCO), a wholly owned subsidiary of INPEX, holding the remaining 12 per cent.
PROJECT TIMELINE
Feasibility Study : Q1 – 2019
FEED : Q2 – 2019
PMC ITB : Q4 – 2019
PMC : Q2 – 2020
EPC ITB : Q2 – 2023
EP : Q2 – 2024
Construction : Q2 – 2024
Commissioning : Q1 – 2027
Completion : Q1 – 2027

