Eni has secured approval from Indonesian authorities for the Plan of Development (POD) for the Geliga gas field in the Ganal Production Sharing Contract (PSC), marking a milestone in unlocking an estimated 8 trillion cubic feet (Tcf) of gas resources across the Geliga and Gula fields in the Kutei Basin.
The approval, granted just six months after the Geliga
discovery, strengthens Eni’s position in Indonesia’s gas sector and advances
plans to establish a third major production hub in the basin.
The development will include 5.9 Tcf of gas in place and 250
million barrels of associated condensate from Geliga, alongside 2.2 Tcf of gas
in place from the existing Gula discovery.
Production from the integrated Geliga/Gula hub is expected
to reach peak levels of approximately one billion cubic feet per day (Bcf/d) of
gas and 50,000 barrels of condensate per day.
The project will complement the producing South Hub and the
North Hub, which is currently under development following a final investment
decision announced earlier this year.
Together, the three
hubs are expected to enable Eni to achieve gross production of around 3 Bcf/d
of gas and 140,000 barrels of condensate per day in East Kalimantan by the end
of the decade.
The additional production will supply both domestic and
international markets, using existing regional infrastructure, including the
Bontang liquefied natural gas (LNG) plant and the Jangkrik Floating Production
Unit (FPU).
New FPSO and subsea infrastructure
The Geliga/Gula development will comprise 15 subsea wells,
associated flowlines and a newly constructed floating production, storage and
offloading (FPSO) vessel.
The FPSO will have processing capacity of approximately 1
Bcf/d of gas and 80,000 barrels of condensate per day, alongside storage
capacity of 1.4 million barrels.
Gas will be processed onboard the FPSO before being
transported through pipelines to the Santan Terminal and the East Kalimantan
gas network. A portion of the output will be liquefied at the Bontang LNG
facility, while the remaining volumes will be delivered to Indonesia’s domestic
market through the pipeline network.
Condensate will be stabilised and stored onboard the FPSO
before being transferred to shuttle tankers for transportation.
The development is expected to benefit from synergies with
the North Hub project, which is scheduled to begin production in 2028. These
synergies are anticipated to help optimise project costs and accelerate
execution timelines.
Strengthening Indonesia's gas supply
The Geliga project, together with the ongoing North Hub and
Gendalo-Gandang developments, forms part of Eni’s wider strategy to expand
natural gas production in Indonesia through its strategic partnership with SKK
Migas.
The projects are expected to support local content
development, increase utilisation of available capacity at the Bontang LNG
plant and provide additional supplies for domestic consumption.
The Geliga field is now operated by Searah, an independent
upstream energy company established through a strategic partnership between Eni
and PETRONAS. Its approval represents another milestone in developing Eni’s
legacy assets in the Kutei Basin and reflects the company's focus on
exploration, accelerated project execution and disciplined delivery.
Eni and PETRONAS expand regional partnership
Established in June 2026, Searah is equally owned by Eni and
PETRONAS, with each company holding a 50 per cent stake. The venture combines
the partners’ portfolios, technical capabilities and regional expertise across
Indonesia and Malaysia.
Its portfolio comprises 19 producing and development assets,
including 14 in Indonesia and five in Malaysia. Searah currently produces
approximately 350,000 barrels of oil equivalent per day (kboe/d), with
ambitions to exceed 500,000 kboe/d of sustainable production by 2028.
Eni also directly operates the Peri-Mahakam PSC, Makassar
Strait PSC and the recently awarded Sapukala Block. In October 2026, the
company signed two binding agreements to sell interests in selected Indonesian
upstream assets operated by Searah to Pertamina and Medco.
The latest Geliga approval follows the recent start-up of the Maha project and further advances Eni’s plans to develop Indonesia’s significant gas resources. With three production hubs planned in the Kutei Basin, the company is positioning East Kalimantan as a major regional gas and condensate production centre, supporting domestic energy requirements and international LNG markets. -OGN/TradeArabia News Service