A TAQA stand
Abu Dhabi National Energy Company (TAQA), Emirates Water and Electricity Company (EWEC), Saudi Arabia's Aljomaih Energy and Water Company, and Singapore's Sembcorp Industries have reached financial close for the AED7.76 billion ($2.1 billion) Taweelah C Independent Power Plant in Abu Dhabi.
The 2.6-gigawatt (GW) project is primarily financed through senior debt from local and international lenders, including HSBC, DBS, OCBC, KfW International Project and Export Finance Bank, Industrial and Commercial Bank of China, and First Abu Dhabi Bank. These institutions, alongside Abu Dhabi Islamic Bank and Dubai Islamic Bank, coordinated and arranged the financing.
The milestone follows the signing of a power purchase agreement in June, under which EWEC will purchase the electricity generated by the facility through the end of 2050.
TAQA stake at 60%
TAQA holds a 60% stake in the project company, while the Aljomaih-Sembcorp consortium owns the remaining 40%. The ownership structure is reversed for the operations and maintenance company, in which the international partners hold 60%, and TAQA owns 40%.
China Energy Engineering Corporation has been awarded the engineering, procurement, and construction (EPC) contract, with commercial operations scheduled to begin in 2029.
TAQA Chief Investment Officer Frank Possmeier said early work was already under way and that the company was leading the next phase of development.
Abu Dhabi’s growing electricity demand
Taweelah C will use high-efficiency combined-cycle gas turbine technology to provide flexible electricity generation, helping balance the intermittent output of solar power as Abu Dhabi expands renewable capacity. The plant is also designed to accommodate the potential use of carbon capture technologies in the future.
EWEC expects electricity demand to increase through 2050, driven by population growth, urban development, and the expansion of data centers supporting artificial intelligence (AI) applications.
To meet this demand, the utility is targeting 15.5 GW of solar photovoltaic capacity by 2030 and more than 35 GW by 2035, increasing the need for generation facilities capable of adjusting output as renewable supply fluctuates.
EWEC Chief Assets Officer Mohamed Almarzooqi said the project would provide operational flexibility to support renewable integration and maintain grid stability, describing its electricity tariff as one of the most competitive in the region.
TAQA's generation expansion
The development contributes to TAQA's ambition to reach 150 GW of gross power generation capacity by 2030, including 50 GW from flexible gas-fired generation.
The Abu Dhabi-based utility has continued investing in power, water, and transmission infrastructure. Its capital expenditure increased 38% year-over-year to nearly $2 billion (AED7.2 billion) in the first half of 2026, according to its financial results.—TradeArabia News Service