Name of Client : Adma-Opco – Abu Dhabi Marine Operating Company – Adnoc Offshore
Budget : $155 million
Facility Type : Pipeline
Sector : Oil
Status : Construction
Location : Abu Dhabi
Feed : Technip
Main Contractor : NPCC – National Petroleum Construction Company
Background
Adnoc Offshore announced plans to develop a Bu Haseer project in the Emirate of Abu Dhabi. The project will focus on wellhead tower and pipeline development.
Project Status
May 2018: Construction is being undertaken. Final construction works are taking place.
February 2018: The completion is still expected in mid-2018. Until then further construction is taking place.
Project Scope
• Construction and installation of a import platform
• Construction and installation of 1 wellhead
• Pipeline
• Cable
Project Schedules
Feasibility Study Q3-2015
Feed Q3-2015
EPC ITB Q1-2016
Engineering & Procurement Q2-2016
Construction Q4-2016
Completion Q2-2018
Project Finance
Adnoc Offshore, formerly known as Adma-Opco, is the project client.