Name of Client : Kuwait Oil Company (KOC)
Estimated Budget : $338,000,000
Facility Type : Water Treatment, Water Injection, Water Injection, Pipeline
Sector : Exploration & Upstream Production, Water, Pipeline, Onshore
Location : Northern Kuwait, Kuwait
Award Date : 2025-Q3
Background
Kuwait Oil Company (KOC) plans to construct a separation facility at GC-25 as well as water injection facilities at GCs-29 & 30.
Project Scope
The project scope includes a separation facility with 300 million barrels of liquid per day (mblpd) capacity and an effluent water treatment facility with 240 million barrels of water per day (mbwpd) capacity at GC-25 with a centralised laboratory, centralised water injection facility at GC-30 with a 500 mbwpd capacity, and modified pipeline connections.
Project Status
As of July 2025, the bidding deadline for the main contract has been extended to August 10, 2025.
Project Finance
Kuwait Oil Company (KOC) is the client of the project.
Project Schedules
Project Announced : 1Q-2023
EPC ITB : 4Q-2024
EP : 3Q-2025
Completion : 1Q-2027