Name of client : Saudi Aramco – Saudi Arabian Oil Company
Budget : $500 million
Facility type : Refinery
Sector : Petrochemicals refining
Status : EPC
Location : Jizan
Feed : KBR (Kellogg Brown & Root)
PMC : KBR (Kellogg Brown & Root)
Main contractor : SKEC – SK Engineering and Construction
Background
Saudi Aramco, in partnership with the Ministry of Petroleum and Mineral Resources (MOPM), plans to build a crude distillation unit (CDU) and vacuum distillation unit (VDU) as part of the Jizan Export Refinery. The unit aims at fractionating mix crude into different streams that will be used for further processing in downstream units.
Project status
March 2013:Engineering works are still ongoing.
December 2012: Aramco has revealed that engineering works have commenced. Construction of the units is expected to begin in August 2013, with project completion slated for 2016.
Project Scope
The general scope of the project involves the construction of CDU / VDU, flare, pipe rack and associated facilities.
In February 2012, KBR has won the Feed and PMC contracts. As per the agreement, they will help in developing the process design, layout, integration and optimization of the refinery. Moreover, they will also develop equipment and material specifications, prepare EPC bid packages and develop an estimate for the construction of the refinery.
Project Schedule
Feed Q1-2011
PMC Q1-2011
EPC Q4-2012
Construction Q1-2013
Completion Q4-2016