QatarEnergy - South Fuel Depot and Multiproduct Pipelines

0/0

Name of Client        : QatarEnergy

Budget                       : $300,000,000

Field Type                 : Greenfield

Facility Types           : Storage Tanks & Offsites

Sector                         : Refining

Main Contractor     : Consolidated Contractors Company (CCC)

Location                    : Ras Laffan, Qatar

EPC Award                : Q3 – 2026


BACKGROUND

QatarEnergy has decided to build a New Fuel Depot (NFD) in the South of Doha to replace the existing Abu Hamour depot to mitigate the risk of a single supply source. 

Abu Hamour depot, the only distribution facility in Qatar, receives gasoline and light gas oil (diesel) from QatarEnergy Refinery located in Mesaieed Industrial City (MIC), via an 18-inch multi-product pipeline, where the product is loaded via loading gantry into trucks for distribution to fuel stations across the state. 

Gasoline and diesel will continue to be supplied to the NFD from QatarEnergy Refinery, while diesel will be supplied from RLIC facilities.


PROJECT SCOPE

The scope of work covers the construction of a new fuel depot, including multiproduct pipelines, a tank farm comprising 16 tanks with a capacity of 10,000 cubic meters each, a pump station, loading and diesel loading facilities, and associated product handling and metering systems. 

The project also includes fire protection and waste management systems, water supply and utility pumps, gantry loading arms, control, safety and communication systems, electrical infrastructure, and other utility and safety support facilities. 

Supporting infrastructure will include an administration building, dispatch and drivers’ buildings, fire station, guard room, substations, mosque, gate house, warehouse, control building and other site infrastructure facilities.


PROJECT STATUS

Actual construction work will begin in November/December 2026.


PROJECT FINANCE

QatarEnergy is the client.


PROJECT SCHEDULE

Project Announced      : Q3 – 2024

FEED                               : Q3 – 2024

EPC ITB                         : Q2 – 2025

EP                                 : Q3 – 2026

Construction                 : Q4 – 2026

Completion                   : Q3 – 2029