Project Budget ($ US) Facility Status
Adco – 1.8 mmbpd Phase 1 Development Project, 1,700,000,000, Oil Field Development, PMC ITB
Adco – Bab Field New Gas Compressors Installation, 300,000,000, Gas Production, EPC ITB
Adco – Jebel Dhanna 1.8 Million Barrel Crude Oil Storage Tank, 1,700,000,000, Oil, FEED ITB
Adco – Jebel Dhanna Tank Farm Facilities Upgrade, 70,000,000, Oil Storage Tanks, EPC ITB
Adco – Sahil-Asab-Shah (Sas) Full Field Development (Onshore), 1,400,000,000, Oil Field Development, EPC ITB
Adco – South Bu Hasa Gas Lift & WAG, 25,000,000, Enhanced Oil Recovery (EOR), EPC
Adgas – Das Island LNG Jetty & Storage Tanks, 115,000,000, Liquefied Natural Gas (LNG), Feasibility Study
Adma Opco – Nasr Field Development, 2,000,000,000, Oil Field Development, FEED
Adma Opco – Offshore Crude & Water Supply Lines Replacement in Umm Shaiif, 1,100,000,000, Offshore Platform, FEED
Adma Opco – Replacement of buried pipework in STOREX Area, 51,000,000, Oil, EPC
Adma Opco – Umm Shaif Gas Injection Facilities (USGIF), 1,600,000,000, Gas Re-Injection, EPC
Adma Opco – Wellhead Revamp & Scada System Replacement in Zakum & Umm Shaif, 20,000,000, Gas Processing, EPC ITB
Adma Opco – Zakum Gas Processing Facilities, 500,000,000, Gas Processing, EPC
Adnoc – Nitrogen Production Plant, Unknown, Nitrogen, Feasibility Study
Adnoc – Offshore Hail Sour Gas Field Development, Unknown, Gas Field Development, EPC ITB
Adnoc – Onshore Shah Sour Gas Field Development, 10,000,000,000, Gas Field Development, Feasibility Study
Adnoc FOD – New Natural Gas Pipeline Network, 300,000,000, Gas, FEED
Atlantis UAQ LTD – Umm Al Qaiwain (UAQ) Field Development, 70,000,000, Gas Field Development, EPC
Borouge – Borouge II (Step 3) – Ethane Cracker, 1,300,000,000, Ethane Cracker, EPC
Borouge – Borouge II (Step 3) – Olefin Conversion Unit, 300,000,000, Alpha Olefins, EPC
Borouge – Borouge II (Step 3) – Overview, 3,100,000,000, Petrochemical Complex, EPC
Borouge – Borouge II (Step 3) – Polyolefins Package, 1,850,000,000, Polyolefins, EPC
Borouge – Borouge II (Step 3) – Utilities and Offsites, 1,230,000,000, Offsites & Utilities, EPC
Borouge – Ruwais Melamine Plant, 175,000,000, Melamine, FEED ITB
Crescent Petroleum – Mubarak Field Development, 30,000,000, Oil Field Development, EPC
Del – Taweelah to Qidfa Gas Feedstock Pipeline, Unknown, Gas, EPC ITB
DMCC – LNG IMPEL – TECHNO PARK – LNG Storage & Trading Facility, 1,000,000,000, LNG EPC ITB
Emalab – Catalysts & Absorbents, Unknown, Catalysts, EPC
Enoc – Jebel Ali Condensate Refinery Phase 2, 350,000,000, Condensate Refinery, EPC
Gasco – 3rd NGL Train at Ruwais (EPC IV), 1,400,000,000, Gas Processing, EPC
Gasco – Adgas – Alternatives To Handle Offshore Associated Gas (OAG) – Overview, 1,500,000,000, Gas, EPC
Gasco – Adgas – OAG Package 2 – Subsea Pipeline from Das Island to Ras Al Quila, 241,000,000, Submarine Gas Pipeline, EPC
Gasco – Adgas – OAG Package 3 – Terminal & Pipeline From Ras Al Qila to Habshan, 400,000,000, Submarine Gas Pipeline, EPC
Gasco – Asab Gas Development Phase II (EPC III), 400,000,000, Gas Field Development, EPC
Gasco – Asab Gas Plant Modifications, Unknown, Gas Field Development, PMC ITB
Gasco – Bu Hasa Debottlenecking, 50,000,000, Gas Production, On Hold
Gasco – Habshan Gas Complex Expansion (HGCE), 1,000,000,000, Gas Production, EPC
Gasco – Habshan to Bu Hasa Gas Pipeline, 40,000,000, Gas, EPC
Gasco – Integrated Gas Development (IGD), 7,500,000,000, Gas Field Development, FEED
Gasco – Onshore Gas Development Phase III (OGD III) (EPC II), 1,460,000,000, Gas Gathering, EPC
Gasco – Replacement of NGL Pipeline Network Project, 250,000,000, Gas, EPC ITB
IPIC – Fujairah Refinery, 5,000,000,000, Refinery, Feasibility Study
IPIC – Habshan to Fujairah Pipeline, 500,000,000, Oil, FEED
ME Natural Gas – Petropars – OOC – Iran to Oman Gas Pipeline, Unknown, Gas, Feasibility Study