Name of Client Saudi Aramco - Saudi Arabian Oil Company
Budget $367 million
Facility Type Gas
Sector Pipeline
Status Construction
Location Central Region
Feed Wood
Main Contractor Arkad (formerly Saudi Kad)
Background
The purpose of the MGS Expansion is to meet increased demand in the Central and Western regions by providing 12.5 BSCFD of Gas by 2020 through the installation of new pipelines and booster gas compression stations. Saudi Aramco’s Master Gas System Expansion (MGSE) is aimed at expanding gas supply for power generation and industrial use in the kingdom. Package 2 entails the construction of 226 kilometers of 46-inch pipeline on the East-West Qassim Gas Pipeline 1.
Project Status
December 2018: Up to this point, only 25 km of lowering of pipelines are remaining with stations and facilities following closely behind.
Project Scope
The scope includes the construction of 226 km of 46" pipeline on the East-West Qassim Gas pipeline 1.
Project Finance
Saudi Aramco is the client for this project, investing about $1.5 billion in MGSE Phase 2.
Arkad signs a $54 million facility agreement with Apicorp to fund its ongoing works in package 2 of Aramco’s Master Gas System Expansion (MGSE).
Project Schedules
Project Announced Q3-2013
Feed Q4-2013
EPC ITB Q1-2015
Engineering & Procurement Q1-2016
Construction Q4-2016
Completion Q4-2018