Name of Client : Saudi Arabian Oil Company (Aramco)
Estimated Budget : $1,300,000,000
Revised Budget : $2,000,000,000
Facility Type : FPF (Field Processing Facility)
Sector : Exploration & Upstream Production
Main Contractor : JGC Corporation
Location : Zuluf, Saudi Arabia
Award Date : 2022-Q2
Background
Aramco considers the expansion of Zuluf oilfield to boost production of Arabian Heavy crude. Zuluf Field, a super-giant oil field located in the Arabian Gulf, approximately 40 km offshore the north-east coast of Saudi Arabia, is undergoing expansion to increase its production capacity. The oil field is present at a shallow water depth of approximately 40 m. The expansion project will increase the production capacity of the field from 800,000 barrels per day (bpd) of Arabian medium crude oil to 1.4 million bpd of heavy crude oil. The Zuluf development will have onshore components split in packages.
Project Status
As of August 2024, Noor Prefab Buildings has completed the delivery and installation of buildings, including mess halls, mosques, and guard houses.
Project Scope
The project scope encompasses the onshore construction work of processing facilities, which includes the installation of two gas-oil separation trains, each with a capacity of 300,000 bpd, a produced water-oil separation plant, chemical injection skids, a crude shipping facility, gas compression systems, treatment facilities, laying of pipelines, installation of security systems, a hydrocarbon processing facility, and a crude storage facility.
LSTK Denys Arabia scope is to detail design, procure and construct new facilities to deliver produced hydrocarbons from the proposed ZCPF to its designated customers by installing several downstream pipelines.
Project Finance
Aramco is the project client.
Project Schedules
Project Announced : 3Q-2017
FEED : 4Q-2017
PMC : 4Q-2017
EP : 2Q-2022
Construction : 3Q-2022
Completion : 1Q-2025