Hitachi Energy has been selected by Pattern Energy to supply its high-voltage direct current (HVDC) and other advanced technologies for the SunZia Transmission Project.
 
It will connect the 3,500-megawatt (MW) SunZia wind project in New Mexico to the power grid in Arizona and Southern California, which will be among the world’s largest transmission links delivering renewable energy.
 
Hitachi Energy’s HVDC Light technology will efficiently transfer and integrate huge volumes of wind power over more than 885 kilometers (550 miles) into the regional power grid. This will significantly increase the availability of sustainable energy for homes and businesses throughout the region.
 
When complete, SunZia Wind will have a total power capacity of 3,500 MW, enough clean, renewable electricity to provide power to approximately three million Americans. The HVDC link will efficiently transmit up to 3,000 MW of this power west to Arizona.
 
The HVDC Light system will be the largest voltage source converter (VSC) installation in the US, one of the largest worldwide, and one of the country’s longest HVDC connections.
 
Niklas Persson, Managing Director of Hitachi Energy’s Grid Integration business, said: “We are proud to be advancing a sustainable energy future for all in the southwestern United States, enabling Pattern Energy to integrate emission-free electricity into the regional grid serving Arizona and Southern California. Our market-leading HVDC technologies combined with our execution expertise makes us the partner of choice to help the U.S. achieve its carbon-neutral targets by efficiently and reliably maximising its renewable energy resources.”
 
Hunter Armistead, CEO of Pattern Energy, said: “Our collaboration with Hitachi Energy is an important milestone for the SunZia Transmission Project and will enable us to harness and carry this great energy potential to the areas where there is a high demand for renewable energy. The use of HVDC technology will enhance power grid reliability and resilience and play a vital role in delivering clean energy and deploying a sustainable energy system in the US”
 
The SunZia Transmission project is a 3,000 MW HVDC link between Corona, New Mexico and Pinal County, Arizona. Hitachi Energy has already started work on designing and engineering the two HVDC Light converter stations, one at either end of the link.
 
The transmitting station converts the power from AC to DC for transport in the overhead lines, then back to AC for integration into the receiving grid.
 
Hitachi Energy has partnered with Quanta Services, (Quanta) to provide a turnkey project solution for the SunZia project, including managing the HVDC construction and building installation at the associated project sites.
 
Quanta is an industry leader providing specialised infrastructure solutions to the utility, renewable energy, communications, pipeline, and energy industries. The HVDC converter stations are expected to be in-service by the end of 2025 to support final testing and commissioning of the SunZia Wind facilities in 2026.-TradeArabia News Service