Name of Client : Adnoc Onshore
Estimated Budget : $600,000,000
Facility Type : Oil Field Development
Sector : Oil
Status : Construction
Location : Abu Dhabi
FEED : SNC Lavalin
PMC : CH2M Hill
Main Contractor : Petrofac, China State Construction Engineering Corporation (CSCEC)
Contract Value : $580,000,000
Background
Adnoc Onshore is developing the Qusahwira field as part of the South East Full Field Development, which includes the development of Asab Sahil, Qusahwira and Mender oil fields. The Qusahwira oil field is located approximately 260 km south of Abu Dhabi and covers an area of 7,525 sq km. Phase 2 of Qusahwira oil field will add 25,000 barrels of oil per day to its current output. It is part of the South East Asset, which contributes approximately one-third of daily production. The project intends to deploy all the enhanced oil recovery (EOR) techniques in order to maintain the targeted production plateau as long as possible.
Project Status
In May 2020, minor construction activities were still being carried out at the field.
Project Scope
The project’s scope of work includes new gas injection compressors, new main oil line (MOL) booster pumps, water-disposal pumps, new water-alternating gas (WAG) wells, flow lines and flow meters, production separators, associated facilities, 75 wells, 24 well pads, gas injection compressors, 3 gathering stations, 3 water injection clusters, and major modification to the CDS. The scope of work for the fire and gas system includes mechanical design, fabrication drawings, supply of all materials, fabrication, supply of spares, documentation of firefighting and safety equipment according to manufacturer’s standard.
Project Finance
Abu Dhabi National Oil Company (ADNOC) Onshore is the project client (formerly ADCO).
Project Schedules
Feasibility Study: 3Q-2013
Award Date: Q2-2019
FEED: 2Q-2014
On Hold: 4Q-2016
EPC ITB: 2Q-2017
Engineering & Procurement: 2Q-2019
Construction: 3Q-2019
Completion: 3Q-2023