Name of Client : Saudi Arabian Oil Company (Aramco)

Estimated Budget : $500,000,000

Revised Budget : $1,500,000,000

Contract Value : $1,200,000,000

Facility Type : Gas Processing

Sector : Gas

Main Contractor : Samsung Engineering Company

Location : Al Jafurah, Saudi Arabia

Award Date : 2021-Q4

Status : Construction


Background

The Gas Processing Facility Package is part of the Jafurah gas terminal that will process up to 1.1 billion cu ft per day (Bcf/D) of unconventional (shale) raw gas from nearby areas, producing sales gas, ethane, natural gas liquids and condensate. The Jafurah gas plant is expected to be a key element of Aramco's long-term strategy to boost its unconventional gas production to 3 Bcf/D during the next decade.


Project Status

As of March 2024, Zamil Process Equipment Company has completed and transported the final equipment for the demethanizer column of the gas processing facility.

Additionally, on February 2024 Baker Hughes has assembled and packaged the first two compressor skids at the Baker Hughes Dammam Facility for Samsung Engineering.


Project Scope

The project scope for the gas processing facility package includes two trains, each handling about 550 million cu ft per day of raw gas.

The process units would include, gas separation, acid gas removers, ngl equipment, and associated surface facilities required for the gas plant.

Other works involve installation of inlet gas slug catcher, installation of inlet condensate separator, installation of coalescer feed pumps, booster compressors, construction of emergency diesel generator building, construction of process interface building construction of chemical storage shelter, and construction of ome building and sub-stations.


Project Finance

Saudi Aramco is the project client.


Project Schedules

Project Announced: 3Q-2019

EPC ITB: 3Q-2019

FEED: 1Q-2020

On Hold: 4Q-2020

EPC ITB: 3Q-2021

EP: 4Q-2021

Construction: 2Q-2023

Completion: 2Q-2024