Name of Client : Saudi Arabian Oil Company (Aramco)
Estimated Budget : $1,200,000,000
Contract Value : $800,000,000
Facility Type : Gas Treatment Plant
Sector : Gas
Main Contractor : Saipem
Location : Marjan, Saudi Arabia
Award Date : 2019-Q21
Status : Construction
Background
Aramco plans to develop the Marjan Oilfeild Expansion Package 10, which involves the construction of a gas treatment and sulphur recovery facility. Marjan oil field delivers a high volume of associated gas and the new oil capacity will replace in time declines in oil capacity from other fields elsewhere. Marjan is estimated to have the capacity to produce about 500,000 barrels per day of crude based on existing production facilities. Aramco's extensive operations, both offshore and onshore are expected to maintain production on the mature gulf fields over the next decade as hundreds of new wells will be required to be drilled to support other operations in nearby oil fields.
Project Scope
The scope of the project involves gas treatment facility and sulphur recovery facility. In addition, a 6 million sq m site preparation will involve roadworks, storm water drainage, type 4 security fence, and solar lighting system.
Project Status
As of May 2023, Tamimi Industrial Services Company (TIS) has successfully completed 600,000 diameter (DIA) inches of the fabrication of carbon steel and stainless steel pipe spool for package 10.
Project Finance
Aramco is the client of the project.
Project Schedules
Project Announced : 1Q-2018
EPC ITB : 3Q-2018
EP : 2Q-2019
Construction : 4Q-2021
Completion : 2Q-2023