Name of client : Adgas – Abu Dhabi Gas Liquefac tion Company
Budget : $420 million
Facility type : Gas Field Development
Sector : Gas
Status : Construction
Location : Abu Dhabi
PMC : Mott MacDonald
Main Contractor : NPCC – National Petroleum Con struction Company
Background
Abu Dhabi Gas Liquefaction Co. Ltd (Adgas) is planning to implement integrated gas development expansion E1 and E2 at Das Island. This project is therefore a part of the company’s target to increase gas production to 2.4 billion standard cubic feet (scf) per day by 2017.
Project status
April 2016: NPCC is carrying out works on the phase 2 offshore section at the moment.
Project scope
The scope of work for IDG-E overall includes:
• Integrated gas development expansion of the existing facilities
• Expansion/construction of the pipeline
• Associated facilities
The phase 2 will mainly focus on the works related to pipeline.
Project finance
Adgas shareholders involve:
Abu Dhabi National Oil Company (Adnoc) 70 per cent
Mitsui & CO. LTD 15 per cent
BP 10 per cent
Total 5 per cent
Project schedule
Feasibility Study Q1-2012
Engineering & Procurement Q2-2016
Construction Q3-2016