Name of Client : Saudi Aramco
Estimated Budget : $5,000,000,000
Main Contractor : China Offshore Oil Engineering Corporation (COOEC); McDermott International
Facility Type : GOSP
Sector : Oil
Location : Marjan, Saudi Arabia
Award Date : 2019-Q1
Background
As a part of Marjan oilfield expansion, Aramco plans to build the Gas Oil Separation Plant (GOSP)-4 complex, which will be designed to handle 475,000 bpd of oil, 813,000 bpd of liquids and almost 750 million cu ft per day of gas. Aramco plans to develop its gas-driven fields such as Marjan offshore field.
Project Status
As of January 2022, Heerema Marine Contractors has won a contract with McDermott to transport and install six large jackets for Package 1 of the Marjan Field Expansion.
Project Scope
The project scope involves the removal and salvage of existing gas turbine generators; installation of two 115-kv subsea power and communication cables; replacement of two platform decks. It also includes various facilities and platforms, gas compression platform, tie-in platform, etc. Additionally, it includes one 36-inch subsea oil trunk line totaling 100 km, and two subsea cables to connect the offshore facilities to the Marjan field’s existing onshore facilities. Under McDermott's contract, 3W Networks will provide a transmission system.
Project Finance
The project client is Aramco.
Project Schedules
Project start: 4Q-2014
FEED: 3Q-2017
EPC ITB: 1Q-2019
EP: 1Q-2019
Construction: 3Q-2021
Completion: 1Q-2024