Terra-Gen, one of the largest independent, integrated renewable energy producers in the US, jointly owned by Masdar and Igneo Infrastructure Partners, announced that its Lockhart Solar PV IV project has reached commercial operations.
The 80-megawatt (MW) solar project in San Bernardino County,
expands Terra-Gen’s renewable energy portfolio in California and will provide
enough electricity to power approximately 40,000 homes and businesses annually
through a long-term power purchase agreement with a California load-serving
entity.
“We are excited to bring the Lockhart IV project online and
continue investing in projects that help meet the growing electricity demand
and create economic, social and environmental positive impact,” said John
O’Connor, chief executive officer of Terra-Gen. “With more than 15 GW of
projects in our development pipeline, we are well positioned to continue
delivering reliable, sustainable energy at scale that can help satisfy the
energy needs of today and tomorrow.”
Construction of the Lockhart IV project created more than
220 jobs at peak activity, and crews completed over 122,000 work hours with no
lost-time incidents.
Cupertino Electric served as the project’s engineering,
procurement and construction contractor.
The Lockhart IV project is the final phase of the Lockhart
Solar and Storage facility. With all four phases now operational, the facility
has a total capacity of 365 MW of solar generation and 173.7 MW of battery
storage, enough to meet the annual needs of more than 350,000 homes and
businesses.
Situated on approximately 4,000 acres of private land, the
complete Lockhart Solar and Storage operational facility includes nearly 1
million solar modules and 248 battery enclosures.
The project utilises the existing gen-tie line connecting to
Southern California Edison’s Kramer Junction Substation. -OGN/TradeArabia News Service