Name of Client : KIPIC - Kuwait Integrated Petro-chemical Industries Company
Estimated Budget : $3.33 billion
Facility Type : Liquefied Natural Gas (LNG)
Sector : Gas
Status : Construction
Location : Al Zour
FEED : Wood Group
PMC : Wood Group
Main Contractor : Hyundai Engineering Company
KOGAS - Korea Gas Corporation
Hyundai Engineering & Construction
Background
KNPC plans the LNG regasification terminal which will have a capacity of 1,500 billion British thermal units a day (btu/d) and will include two berths for the simultaneous unloading of large LNG carriers. The terminal will also include four full containment LNG tanks, each with a working capacity of 225,500 cubic meters. It is due to be constructed on reclaimed land formed by hydraulic filling. The LNG terminal will also provide training for plant operators along with testing so they can receive provisional acceptance.
Project Status
October 2019: KIPIC has submerged the longest (500 meters) undersea pipeline for Al Zour LNG project.
Project Scope
The project scope includes:
• Four full containment LNG tanks, each with a working capacity of 225,500 square meters.
• A regasification plant with a capacity of 1,500 billion British thermal units a day.
• Additional utilities and infrastructure needed for the operation of the plant.
• Pipeline connections between the import terminal and the existing pipeline system.
• Metering system.
• Pig launcher/receiver.
• Natural gas send-out pipelines.
• Tie-in with Kuwait Oil Company gas network.
Project Finance
Kuwait National Petroleum Company (KNPC) is the client of the project. KNPC and the Petrochemicals Industries Company (PIC) have signed agreements to transfer contracts of the project to Kuwait Integrated Petrochemical Industries Company (KIPIC).
Project Schedules
Feasibility Study 4Q-2013
FEED 2Q-2014
EPC ITB 1Q-2016
Engineering & Procurement 1Q-2016
Construction 1Q-2017
Completed 3Q-2020