Name of Client : OTTCO – Oman Tank Terminal Company
Budget : $400 million
Facility Type : Oil Storage Terminal
Sector : Oil
Status : Engineering & Procurement
Location : Duqm
FEED : Wood
PMC : WorleyParsons
Main Contractor : China Petroleum Pipeline Engi neering Company – CPPE
Background
Oman Tank Terminal Company LLC (OTTCO) plans to build a massive crude oil storage hub at Ras Markaz near Duqm. The storage hub will also serve as an alternative export terminal for Omani crude in the event of supply disruptions affecting the national’s only crude export terminal at Mina Al Fahal in Muscat Governorate.
Project Status
August 2018 OTTCO selects China Petroleum Pipeline Engineering Company as the winning contractor for the EPC contract. A formal award will be announced once all the formalities are completed.
Project Scope
The first phase of the project includes the establishment of:
• 8 tanks with an estimated capacity of 650,000 barrels each
• Floating platforms for the import and export of oil
• 7km-long undersea pipelines for receiving and exporting oil
• A pumping station
Project Finance
Oman Tank Terminal Company LLC (OTTCO) is the client.
Project Schedule
Feasibility Study 4Q-2012
Feed ITB 3Q-2013
Feed 1Q-2015
EPC ITB 4Q-2015
Engineering & Procurement 3Q-2018
Completion 3Q-2021